PORT MARINE NOTICE NO. 96 OF 2025 - RSYC PARAPET WALL RECTIFICATION WORK

17 Jul 2025 6:50 PM | Secretariat SBIA (Administrator)


PORT MARINE NOTICE NO. 96 OF 2025.pdf

As of 17 July 2025, rectification works have commenced on the parapet wall at the Republic of Singapore Yacht Club (RSYC) breakwater and are scheduled to continue until 16 January 2026, according to Port Marine Notice No. 96 of 2025 issued by the Maritime and Port Authority of Singapore (MPA).

Scope of Works

The project includes:

  • Removal of damaged parapet walls

  • Installation of new parapet structures

  • Removal and replacement of affected concrete slabs

Work will take place Monday to Saturday from 0700H to 1900H, subject to site conditions.

Location

The designated working area is just off RSYC and is clearly marked by the following coordinates:

  • 01°17.661’N, 103°45.532’E

  • 01°17.675’N, 103°45.540’E

  • 01°17.659’N, 103°45.568’E

  • 01°17.645’N, 103°45.560’E

(Refer to MPA’s chartlet in the official notice for exact area details.)

Safety Advisory for Mariners

Boaters are strongly advised to:

  • Keep clear of the designated working area

  • Maintain a proper lookout

  • Navigate with caution and at a safe speed

  • Monitor VHF Channel 18 (Pasir Panjang Control) when transiting the vicinity

Approved working craft including crane barges, tug boats, and safety boats will be operating in the area and will display appropriate local and international signals.

Further Information

For project-specific enquiries, contact:

Mr. Alston Lim, Technical Manager

Tel: +65 9641 8685

Email: alston@mtc.com.sg